What is this project?
"Brishyrnot Limestone Deposit-II'' with proposed maximum production capacity of 3.2 MTPA (3.0 MTPA limestone & 0.2 MTPA shale) by Star Cement Meghalaya Limited is an approved mining project in Bri Shyrnot, Khliehriat, East Jaintia Hills, Meghalaya. The site covers 160.6 acres.
Who is building it?
The applicant is Star Cement Meghalaya Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 22 Apr 2026), as of 27 Nov 2026.
Where is it?
In Bri Shyrnot, Khliehriat, East Jaintia Hills, Meghalaya.
How big is it?
It has a stated cost of ₹34 crore and a site of 160.6 acres.
When was it filed?
The application was filed on 11 Nov 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 22 Apr 2026 |
| Application filed | 11 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Star Cement Meghalaya Limited |
| Land area | 160.6 acres (65 ha) |
| Project cost | ₹34 crore |
| Village / locality | Bri Shyrnot |
| Taluk / tehsil | Khliehriat |
| District | East Jaintia Hills |
| State | Meghalaya |
| Location from | Site area on record |
| Our reference | WID-ML-00055 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Nov 2024 (this page) | Environmental approval granted | 160.6 acres | ₹34 crore |
| Early planning filed 30 Dec 2023 | Cleared for impact study | 160.6 acres | ₹34 crore |
In context
65 applications in East Jaintia Hills since January 2022 are in the same category (Mining): 49 approved, 11 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 160.6 acres, this one is larger than 80% of them.
No other mining lease on record is within 500 m of this site; 15 have applied within 5 km.
Where it is
Bri Shyrnot, Khliehriat, East Jaintia Hills, Meghalaya. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Brishyrnot Limestone Deposit-II'' with proposed maximum production capacity… — cleared for impact study, 50 m away
- GVIL Shale Mine — environmental approval granted, 1.9 km away
- GVIL Shale Mine — environmental approval granted, 1.9 km away
- Meghatop Limestone mine with proposed maximum production capcity of 5 MTPA by… — withdrawn, 2.2 km away
- Proposed Lum Padiar Shale Mine (Area 21.16 Ha) with Shale Production Capacity:… — cleared for impact study, 2.6 km away
- Wah Pynkon Limestone Mine (4.739 ha) — under environmental review, 2.6 km away
- Wah Pynkon-2 Limestone Mine (4.518 ha) — under environmental review, 2.7 km away
- Larung Limestone Mine over an area of 4.76 Ha of M/s. JUD Cements Limited — returned to applicant, 2.7 km away
More from Star Cement Meghalaya Limited in East Jaintia Hills
- 8 MW Thermal Power Plant at Lumshnong, East Jaintia Hills District, Meghalaya — environmental approval granted
- 43 MW Thermal Power Plant at Lumshnong, East Jaintia Hills District, Meghalaya — environmental approval granted
- 43 MW imported coal based Thermal Power Plant project at Lumshnong, East… — withdrawn
- 100% Coal-based 8 MW Thermal Power Plant project at Lumshnong, East Jaintia… — withdrawn
- Enhancement in Cement Clinker Capacity from 1.75 MTPA to 2.25 MTPA of Clinker… — initial checks
All 7 Star Cement Meghalaya projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.