Quick answers
What is 2x 600 MW Sub-Critical Coal Based Thermal Power Plant?
2x 600 MW Sub-Critical Coal Based Thermal Power Plant is a proposed power project in Belia, Anuppur, Madhya Pradesh. The site covers 996 acres.
Who is building it?
The applicant is M B Power (Madhya Pradesh) Limited Anuppur.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Belia, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹8,323.5 crore and a site of 996 acres.
When was it filed?
The application was filed on 7 Sept 2023.
Project details
| Official title | 2x 600 MW Sub-Critical Coal Based Thermal Power Plant at Tehsil Jaithari District Anuppur, Madhya Pradesh by M/s MB Power (Madhya Pradesh) Ltd. |
|---|---|
| Status | Initial checks |
| Status since | 7 Sept 2023 |
| Application filed | 7 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | M B Power (Madhya Pradesh) Limited Anuppur |
| Land area | 996 acres (403.1 ha) |
| Project cost | ₹8,323.5 crore |
| Village / locality | Belia |
| Taluk / tehsil | Anuppur |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-01207 |
In context
34 applications in Anuppur since January 2022 are in the same category (Power): 13 approved, 7 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 996 acres, this one is larger than 79% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Belia, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of existing Coal Based Sub-Critical Thermal Power Plant from 2X600… — environmental approval granted, 0 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — lapsed, 50 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — under forest review, 50 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — environmental approval granted, 50 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — cleared for impact study, 50 m away
- Splitting of Environmental Clearance granted for 2,860 MW [2X630 MW (Phase-I)… — more information requested, 100 m away
- Jaithari Gobri Sand Mine — cleared for impact study, 3.3 km away
- New Kanya shiksha parishar Jaithari — forest land use approved, 4.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.