Quick answers
What is this project?
Splitting of Environmental Clearance granted for 2,860 MW [2X630 MW (Phase-I) & 2x800 MW (Phase-II)] Coal-Based Thermal Power Project is a proposed power project in Jaitahari, Jaithari, Anuppur, Madhya Pradesh. The site covers 1,114.9 acres.
Who is building it?
The applicant is Mb Power (Madhya Pradesh) Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Jaitahari, Jaithari, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹28,200 crore and a site of 1,114.9 acres.
When was it filed?
The application was filed on 7 Oct 2026.
Project details
| Official title | Splitting of Environmental Clearance granted for 2,860 MW [2X630 MW (Phase-I) & 2x800 MW (Phase-II)] Coal-Based Thermal Power Project located at Village Laharpur, Murra, Guwari, Belia & Jaithari in Jaithari Tehsil, District Anuppur, Madhya Pradesh to MB Power (Madhya Pradesh) Limited by Splitting/transferring of one (1) unit of 800 MW Coal-Based Ultra Super Critical Thermal Power Unit of Phase-II, along with its associated facilities to Anuppur Powerprojects Private Limited (APPL). |
|---|---|
| Status | More information requested |
| Status since | 18 Nov 2026 |
| Application filed | 7 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Other |
| Sector | Power |
| Applicant | Mb Power (Madhya Pradesh) Limited |
| Land area | 1,114.9 acres (451.2 ha) |
| Project cost | ₹28,200 crore |
| Village / locality | Jaitahari |
| Taluk / tehsil | Jaithari |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-08687 |
In context
34 applications in Anuppur since January 2022 are in the same category (Power): 13 approved, 7 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1,114.9 acres, this one is larger than 85% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jaitahari, Jaithari, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — lapsed, 100 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — under forest review, 100 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — environmental approval granted, 100 m away
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — cleared for impact study, 100 m away
- Expansion of existing Coal Based Sub-Critical Thermal Power Plant from 2X600… — environmental approval granted, 100 m away
- 2x 600 MW Sub-Critical Coal Based Thermal Power Plant — initial checks, 100 m away
- Jaithari Gobri Sand Mine — cleared for impact study, 3.2 km away
- New Kanya shiksha parishar Jaithari — forest land use approved, 4 km away
More from Mb Power (Madhya Pradesh) Limited in Anuppur
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — lapsed
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — under forest review
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — environmental approval granted
- EXPANSION BY ADDITION OF 2x800 MW (1600 MW) COAL BASED ULTRA SUPER CRITICAL… — cleared for impact study
- Expansion of existing Coal Based Sub-Critical Thermal Power Plant from 2X600… — environmental approval granted
All 6 Mb Power (Madhya Pradesh) projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.