Project details
| Official title | Expansion of existing Sponge iron 91,520 TPA to proposed final capacity of Sponge iron 511,500 TPA, Pelletization Plant 1,600,000 TPA with PGP – 22500 Nm3/hr, M.S. Billets 211,200 TPA, Rolling Mill 204,800 TPA, Briquetting Plant 122,830 TPA, Submerged Arc Furnace for Ferro Alloy 2x12 MVA, Metal Recovery Plant 79,200 TPA & CPP 68 MW (WHRB 38 MW & AFBC 30 MW), at Village - Kalunga, Tehsil – Lathikata, District – Sundergarh, Odisha by M/s Times Steel and Power Private Limited |
|---|---|
| Status | Lapsed |
| Status since | 5 Apr 2025 |
| Application filed | 5 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Times Steel & Power Private Limited |
| Land area | 82.4 acres (33.4 ha) |
| Project cost | ₹650 crore |
| Village / locality | Brahmanataranga |
| Taluk / tehsil | Brahmani Tarang |
| District | Sundargarh |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00486 |
In context
57 applications in Sundargarh since January 2022 are in the same category (Industry): 17 approved, 18 filed or under review, and 22 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 82.4 acres, this one is larger than 63% of them.
33 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Brahmanataranga, Brahmani Tarang, Sundargarh, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 9.548 Ha of forest area proposed for diversion for the Project… — under forest review, 50 m away
- Expansion of existing Sponge iron 1,00,000 TPA to proposed final capacity of… — lapsed, 150 m away
- Proposed Greenfield Project for Installation of 3 x 12 Tonne/ Heat SMS for… — not approved, 400 m away
- Transfer of Environment Clearance letter issued by Ministry of Environment,… — lapsed, 750 m away
- Regularization of existing rolling mill for the production of Rerolled steel… — lapsed, 850 m away
- Enhancement of production capacity of existing Induction Furnace from 0.2 MTPA… — initial checks, 1.1 km away
- Proposed for capacity enhancement of DRI Plant from 2x500 TPD to 2x650 TPD… — initial checks, 1.1 km away
- Expansion of DRI Plant from 0.552 MTPA to 0.783 MTPA, SMS Plant from 0.318… — lapsed, 1.1 km away
More from Times Steel & Power Private Limited in Sundargarh
- Expansion of existing Sponge iron 1,00,000 TPA to proposed final capacity of… — lapsed
- Diversion of 9.548 Ha of forest area proposed for diversion for the Project… — under forest review
All 3 Times Steel & Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.