Expansion of existing implemented project [1x225 m3 MBF (1,88,000 TPA), 1x40 m2 Sinter Plant (4,60,000 TPA), 8x100 TPD DRI Plant (2,40,000 TPA), 2x30 T I.F. SMS (1,07,700 TPA), 1x0.7 MTPA Coal washery, 2x0.12 MTPA Nonrecovery type Coke Oven Plant, 1x0.6 MTPA Pellet plant, 2x4,000 Nm3/hr PGP, 16 MW AFBC, 8x1.0 MW (8.0 MW) WHRB Based CPP from existing DRI Plant] to Integrated Steel Plant of capacity 1.7 Million TPA (Finished Steel) with 275 MW CPP and 1.25 million TPA Cement Grinding Unit is an approved industrial project in Budipadar, Jharsuguda, Odisha. The site covers 266.7 acres.
Who is building it?
The applicant is Orissa Metaliks Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 1 Oct 2024), as of 27 Nov 2026.
Where is it?
In Budipadar, Jharsuguda, Odisha.
How big is it?
It has a stated cost of ₹2,461.3 crore and a site of 266.7 acres.
When was it filed?
The application was filed on 16 Apr 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 1 Oct 2024 |
| Application filed | 16 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Orissa Metaliks Private Limited |
| Land area | 266.7 acres (107.9 ha) |
| Project cost | ₹2,461.3 crore |
| Village / locality | Budipadar |
| Taluk / tehsil | Jharsuguda |
| District | Jharsuguda |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01369 |
In context
38 applications in Jharsuguda since January 2022 are in the same category (Industry): 23 approved, 6 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 266.7 acres, this one is larger than 62% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Budipadar, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (9.7 km away).
Other projects nearby
- Diversion of 5.302 Ha forest land for non-forestry use for Integrated Steel… — lapsed, 50 m away
- Expansion of existing implemented project [1x225 m3 MBF (1,88,000 TPA), 1x40… — cleared for impact study, 50 m away
- Expansion of integrated steel plant (Sponge Iron (10,50,000 TPA); Pig Iron… — environmental approval granted, 50 m away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished… — initial checks, 2.2 km away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished Steel) — initial checks, 2.2 km away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished Steel) — environmental approval granted, 2.2 km away
- Provision of Fly Over — more information requested, 3.8 km away
- H. Katapali Sand Bed-F — lapsed, 4.1 km away
More from Orissa Metaliks Private Limited in Jharsuguda
- Diversion of 5.302 Ha forest land for non-forestry use for Integrated Steel… — lapsed
- Expansion of existing implemented project [1x225 m3 MBF (1,88,000 TPA), 1x40… — cleared for impact study
- Expansion of integrated steel plant (Sponge Iron (10,50,000 TPA); Pig Iron… — environmental approval granted
4 Orissa Metaliks projects in Jharsuguda
All 9 Orissa Metaliks projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.