What is this project?
Integrated Steel Plant in the villages of Udayabata, Nuagarh, and Bijayachandrapur under Kujanga Tahasil of District Jagatsinghpur at Paradeep, Odisha is a proposed industrial project in Udayabata, Paradeep Lock, Jagatsinghapur, Odisha. The site covers 1,484.8 acres.
Who is building it?
The applicant is Arcelormittal Nippon Steel India Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Udayabata, Paradeep Lock, Jagatsinghapur, Odisha.
How big is it?
It has a stated cost of ₹38,000 crore; a site of 1,484.8 acres and 28.6 acres (11.6 ha) of forest land.
When was it filed?
The application was filed on 20 Oct 2023.
Project details
| Official title | Establishment of Integrated Steel Plant in the villages of Udayabata, Nuagarh, and Bijayachandrapur under Kujanga Tahasil of District Jagatsinghpur at Paradeep, Odisha |
|---|---|
| Status | More information requested |
| Status since | 28 Apr 2026 |
| Application filed | 20 Oct 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Industry |
| Applicant | Arcelormittal Nippon Steel India Limited |
| Land area | 1,484.8 acres (600.9 ha) |
| Forest land | 28.6 acres (11.6 ha) |
| Project cost | ₹38,000 crore |
| Village / locality | Udayabata |
| Taluk / tehsil | Paradeep Lock |
| District | Jagatsinghapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04189 |
In context
6 applications in Jagatsinghapur since January 2022 are in the same category (Industry): 4 approved, 2 filed or under review, and 0 withdrawn, lapsed or rejected.
13 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Udayabata, Paradeep Lock, Jagatsinghapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Setting of Integrated Steel Plant for production of 7.0 MTPA Liquid Steel by… — under environmental review, 1000 m away
- Setting of Integrated Steel Plant for production of 7.0 MTPA Liquid Steel by… — cleared for impact study, 1000 m away
- Amalgamation of Environment Clearances (ECs) of Pellet Plant # 1&2 (12 MTPA)… — under environmental review, 1.1 km away
- Amalgamation of EC of Captive Power Plant (2x30 MW) with the EC of Pellet… — returned to applicant, 1.1 km away
- Captive Riverine Jetty of Material Handling Capacity of 4.5 MTPA on River… — environmental approval granted, 1.6 km away
- Captive Riverine Jetty of Material Handling Capacity of 4.5 MTPA on River… — returned to applicant, 1.6 km away
- Expansion of Captive Riverine Jetty Facility with Material Handling Capacity… — lapsed, 1.8 km away
- Ro-Pax Jetty at Musadia — coastal clearance granted, 2.1 km away
More from Arcelormittal Nippon Steel India Limited in Jagatsinghapur
- Setting of Integrated Steel Plant for production of 7.0 MTPA Liquid Steel by… — under environmental review
- Proposed Rehabilitation & Resettlement (R & R) Colony , At. Village… — environmental approval granted
- Laying of 34 inch Dia underground Slurry pipeline by M/s ArcelorMittal Nippon… — lapsed
- Proposed Rehabilitation & Resettlement (R & R) Colony , At. Village… — environmental approval granted
- Expansion of Captive Riverine Jetty Facility with Material Handling Capacity… — lapsed
- Proposed Rehabilitation & Resettlement (R & R) Colony , At. Village… — cleared for impact study
13 Arcelormittal Nippon Steel projects in Jagatsinghapur
All 65 Arcelormittal Nippon Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.