Quick answers
What is this project?
Diversion of 0.0186 Hectares Forest Land by Bsnl for the Installation of Mobile Tower Under 4g Saturation Project of Goi is a proposed telecom project in Kyongnosla Forest Block, Gangtok, East District, Sikkim. The site covers 0 acres.
Who is building it?
The applicant is Mahesh Nair.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Kyongnosla Forest Block, Gangtok, East District, Sikkim.
How big is it?
It has a stated cost of ₹75 lakh; a site of 0 acres and 190 m² of forest land.
When was it filed?
The application was filed on 19 Mar 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 25 Sept 2026 |
| Application filed | 19 Mar 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Mahesh Nair |
| Land area | 200 m² |
| Forest land | 190 m² |
| Project cost | ₹75 lakh |
| Village / locality | Kyongnosla Forest Block |
| Taluk / tehsil | Gangtok |
| District | East District |
| State | Sikkim |
| Location from | Site boundary on record |
| Our reference | WID-SK-00078 |
In context
13 applications in East District since January 2022 are in the same category (Telecom): 2 approved, 4 filed or under review, and 7 withdrawn, lapsed or rejected. At 0 acres, this one is smaller than 82% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kyongnosla Forest Block, Gangtok, East District, Sikkim. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Multi Village Water Supply Scheme under Jal Jeevan Mission — more information requested, 2 km away
- 4G Saturation — more information requested, 3.4 km away
- 4G Saturation — lapsed, 3.4 km away
- Construction of Cavern by 3/11 Gr at General Area of Rajgarh — initial checks, 6.1 km away
- Diversion of Forest Land of 1.6 Ha from Chola to Yak La Pass for operational… — lapsed, 6.8 km away
- Diversion of forest land of 2.38 ha for construction of Rainbow Trout Brood… — more information requested, 8.4 km away
- Diversion of 191.621 Acres Forest Land Between Milestone-4 to Milestone-13 — lapsed, 8.4 km away
- Nature Interpretation Centre at Nathula by Tourism & Civil Aviation… — more information requested, 8.6 km away
More from Mahesh Nair in East District
- 4G Saturation — more information requested
- 4G Saturation — more information requested
- 4G Saturation — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.