Project details
| Official title | Proposed 300 KLPD (2x150 KLPD) Grain/Molasses/Cane juice based distillery, 15 KLPD Malt Spirit plant along with 10 MW Co-generation power plant at Village Abbaspur, Tehsil Mitauli, District Lakhimpur Kheri, Uttar Pradesh by M/s. Globus Spirits Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 8 Dec 2023 |
| Application filed | 20 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Globus Spirits Limited |
| Land area | 36.7 acres (14.9 ha) |
| Project cost | ₹250 crore |
| Village / locality | Abbaspur |
| Taluk / tehsil | Mohammdi |
| District | Kheri |
| State | Uttar Pradesh |
| Location from | Village |
| Our reference | WID-UP-00378 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 20 Oct 2023 (this page) | Environmental approval granted | 36.7 acres | ₹250 crore |
| Early planning filed 29 Nov 2022 | Cleared for impact study | 36.7 acres | ₹250 crore |
In context
14 applications in Kheri since January 2022 are in the same category (Industry): 13 approved, 0 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 36.7 acres, this one is smaller than 86% of them.
Where it is
Abbaspur, Mohammdi, Kheri, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- CGD Network GA-11A.01 — forest land use approved, 176.3 km away
- Protected Forest Land proposed for diversion for Entry/Exit approach to Bharat… — lapsed, 180.4 km away
- Barkhera Soil Mining project — environmental approval granted, 180.6 km away
- Laying of 12" Carbon steel Gas Pipeline along the road by BPCL on… — forest land use approved, 187.2 km away
- Siyaraha Soil Mining Project — under environmental review, 189.6 km away
- Proposed 300 KLPD (2x150 KLPD) Grain/Molasses/Cane juice based distillery, 15… — cleared for impact study, 193.5 km away
- Ordinary Earth excavation from Khasra/Gata No. 841 & 633, Total Area-1.1420 ha — under environmental review, 193.6 km away
- Environmental Clearance of Proposed Ordinary Earth excavation from Khasra/Gata… — environmental approval granted, 195.8 km away
All 8 Globus Spirits projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.