Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 14 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | NTPC Limited (NTPC) |
| Land area | 2,198 acres (889.5 ha) |
| Project cost | ₹1,054.8 crore |
| Village / locality | Umran |
| Taluk / tehsil | Unchahar |
| District | Rae Bareli |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-01504 |
In context
5 applications in Rae Bareli since January 2022 are in the same category (Power): 2 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Umran, Unchahar, Rae Bareli, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Feroze Gandhi Unchahar Thermal Power Project, Stage-I — lapsed, 0 m away
- Feroze Gandhi Unchahar Thermal Power Station, Stage - II (2x210MW) — environmental approval granted, 200 m away
- Expansion by addition of 500 MW (Stage-IV) Coal Based Thermal Power Plant at… — environmental approval granted, 200 m away
- 1x210 MW Feroze Gandhi Unchahar Thermal Power Project (FGUTPP) Stage-III… — returned to applicant, 200 m away
- Proposed protected forest land to be diverted for Entry/Exit approach to IOCL… — forest land use approved, 2.5 km away
- Proposed Forest Land to be Diverted for Entry/Exit Approach to IOCL Retail… — forest land use approved, 9.3 km away
- Waste management project by Ferrosang Enviro Solutions Private Limited — lapsed, 13.4 km away
- Waste management project by Ferrosang Enviro Solutions Private Limited — environmental approval granted, 13.4 km away
More from NTPC Limited (NTPC) in Rae Bareli
- Feroze Gandhi Unchahar Thermal Power Station, Stage - II (2x210MW) — environmental approval granted
- Expansion by addition of 500 MW (Stage-IV) Coal Based Thermal Power Plant at… — environmental approval granted
- 1x210 MW Feroze Gandhi Unchahar Thermal Power Project (FGUTPP) Stage-III… — returned to applicant
- Feroze Gandhi Unchahar Thermal Power Project, Stage-I — lapsed
5 NTPC projects in Rae Bareli
All 129 NTPC projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.