What is this project?
Sand/Moram Mining Project at Betwa River Bed, Gata No. 2118, 2119, Khand No. 03 Area – 6.50Ha Village- Erich, Tehsil- Garautha & District- Jhansi, U.P is a lapsed mining project in Erich, Garautha, Jhansi, Uttar Pradesh. The site covers 16.1 acres.
Who is building it?
The applicant is Mayank Gupta.
Has it been approved?
No. The application was lapsed on 8 May 2026, so it is no longer under consideration.
Where is it?
In Erich, Garautha, Jhansi, Uttar Pradesh.
How big is it?
It has a stated cost of ₹51 lakh and a site of 16.1 acres.
When was it filed?
The application was filed on 4 Sept 2025.
Project details
| Status | Lapsed |
|---|---|
| Status since | 8 May 2026 |
| Application filed | 4 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Mayank Gupta |
| Land area | 16.1 acres (6.5 ha) |
| Project cost | ₹51 lakh |
| Village / locality | Erich |
| Taluk / tehsil | Garautha |
| District | Jhansi |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-03269 |
In context
211 applications in Jhansi since January 2022 are in the same category (Mining): 146 approved, 39 filed or under review, and 26 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 16.1 acres, this one is larger than 72% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 65.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.
Where it is
Erich, Garautha, Jhansi, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance for Sand/Morrum Mining project from Arazi… — lapsed, 450 m away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of River… — lapsed, 450 m away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of River… — cleared for impact study, 450 m away
- Laying of 24 F of Cable From Moth Bsnl Telephone Exchange to Ait Bsnl… — lapsed, 1.7 km away
- Laying of 24 F of Cable From Moth Bsnl Telephone Exchange to Ait Bsnl… — lapsed, 1.7 km away
- Proposed project of Sand/Morrum Mining from Riverbed of Betwa River at Gata… — cleared for impact study, 1.8 km away
- Proposed Diversion for Laying of Water Distribution Line along Gursarai-Erach… — more information requested, 3.2 km away
- River Bed Sand/ Morrum Mining — environmental approval granted, 3.4 km away
More from Mayank Gupta in Jhansi
- Imarati Pathhar- Granite (Khanda Boulder Ballast) Mining in Gata No 515… — environmental approval granted
- Building stone (Khanda, Boulder, Ballast) Sandstone Mining Project, Lease… — environmental approval granted
- Imarati Pathhar- Granite (Khanda Boulder Ballast) Mining in Gata No 515… — cleared for impact study