Application of "No Increase in Pollution Load" Certificate for Change in Configuration of CPP Plant for Power Generation from only CFBC Boiler instead of permitted AFBC and WHRB Boilers and surrendering permitted Producer Gas Plant is a proposed industrial building project in Madandi, Neturia, Puruliya, West Bengal. The site covers 200.4 acres.
Who is building it?
The applicant is Shakambhari Ispat & Power Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Madandi, Neturia, Puruliya, West Bengal.
How big is it?
It has a stated cost of ₹1,318 crore and a site of 200.4 acres.
When was it filed?
The application was filed on 11 Aug 2026.
Project details
| Official title | Application of "No Increase in Pollution Load" Certificate for Change in Configuration of CPP Plant for Power Generation from only CFBC Boiler instead of permitted AFBC and WHRB Boilers and surrendering permitted Producer Gas Plant at Village- Madandih, P.O.- Bartoria, District: Purulia, West Bengal |
|---|---|
| Status | Initial checks |
| Status since | 11 Aug 2026 |
| Application filed | 11 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Shakambhari Ispat & Power Limited |
| Use | Industrial |
| Height | 97 m |
| Land area | 200.4 acres (81.1 ha) |
| Project cost | ₹1,318 crore |
| Village / locality | Madandi |
| Taluk / tehsil | Neturia |
| District | Puruliya |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01777 |
In context
5 applications in Puruliya since January 2022 are in the same category (Buildings & townships): 0 approved, 4 filed or under review, and 1 withdrawn, lapsed or rejected.
19 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Madandi, Neturia, Puruliya, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance due to change in Change in CIN & GSTIN… — environmental approval granted, 0 m away
- Transfer of Environment Clearance due to change in Change in CIN & GSTIN… — withdrawn, 0 m away
- Expansion of Shakambhari Ispat & Power Limited plant for production of 0.7875… — environmental approval granted, 0 m away
- Sponge Iron Plant (4x100 TPD Kilns), Induction Furnaces (3x20 T), 1,40,000 TPA… — environmental approval granted, 950 m away
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — cleared for impact study, 1.9 km away
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — lapsed, 1.9 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 1.9 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 1.9 km away
More from Shakambhari Ispat & Power Limited in Puruliya
- Greenfield Integrated Steel Plant for production of 2.73 MTPA Crude Steel,… — under environmental review
- Application for "No Increase in Pollution Load" Certificate for Change in Raw… — initial checks
- Application of "No Increase in Pollution Load" Certificate for Change in… — initial checks
- Transfer of Environment Clearance due to change in Change in CIN & GSTIN… — environmental approval granted
- Transfer of Environment Clearance from Bravo Sponge Iron Private Limited to… — environmental approval granted
- Expansion of Sponge Iron Plant for Production of 2.1555 Million Tons Per Annum… — environmental approval granted
All 9 Shakambhari Ispat & Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.