Quick answers
What is Expansion of Integrated Steel Complex?
Expansion of Integrated Steel Complex is a lapsed industrial project in Kurud, Arang, Raipur, Chhattisgarh. The site covers 132 acres.
Who is building it?
The applicant is Jsw Ispat Special Products Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Kurud, Arang, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹318 crore and a site of 132 acres.
When was it filed?
The application was filed on 18 Dec 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Integrated Steel Complex
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 18 Dec 2023 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Jsw Ispat Special Products Limited |
| Land area | 132 acres (53.4 ha) |
| Project cost | ₹318 crore |
| Village / locality | Kurud |
| Taluk / tehsil | Arang |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00302 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 18 Dec 2023 (this page) | Lapsed | 132 acres | ₹318 crore |
| Ownership transfer filed 31 Aug 2023 | Environmental approval granted | 132 acres | ₹318 crore |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 132 acres, this one is larger than 86% of them.
106 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kurud, Arang, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Up Gradation of existing Induction Furnaces of 2 x 8T to 2 x 10T &… — initial checks, 0 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 0 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 0 m away
- Proposed "increase in Production Capacity of Existing Ferro Alloy From 44,000… — initial checks, 250 m away
- Proposed Increase in Production Capacity of Existing Rolling Mill Capacity… — initial checks, 600 m away
- Rolling Mill (1,50,000 TPA) in the existing Integrated Steel Plant at Monnet… — environmental approval granted, 650 m away
- Establishment of Rolling Mill (1,50,000 TPA) — withdrawn, 650 m away
- Integrated Steel Plant — withdrawn, 650 m away
More from Jsw Ispat Special Products Limited in Raipur
- Establishment of Rolling Mill (1,50,000 TPA) — withdrawn
- Integrated Steel Plant — withdrawn
4 Jsw Ispat Special Products projects in Raipur
All 5 Jsw Ispat Special Products projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.