Quick answers
What is this project?
Rolling Mill (1,50,000 TPA) in the existing Integrated Steel Plant at Monnet Marg, Mandir Hasaud, Raipur, Chhattisgarh is an approved industrial project in Kurud, Arang, Raipur, Chhattisgarh. The site covers 40.7 acres.
Who is building it?
The applicant is Mivaan Steels Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 16 Sept 2024), as of 27 Nov 2026.
Where is it?
In Kurud, Arang, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹35 crore and a site of 40.7 acres.
When was it filed?
The application was filed on 16 Jul 2024.
Project details
| Official title | Establishment of Rolling Mill (1,50,000 TPA) in the existing Integrated Steel Plant at Monnet Marg, Mandir Hasaud, Raipur, Chhattisgarh |
|---|---|
| Status | Environmental approval granted |
| Status since | 16 Sept 2024 |
| Application filed | 16 Jul 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Mivaan Steels Limited |
| Land area | 40.7 acres (16.5 ha) |
| Project cost | ₹35 crore |
| Village / locality | Kurud |
| Taluk / tehsil | Arang |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00901 |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 40.7 acres, this one is larger than 59% of them.
136 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kurud, Arang, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Establishment of Rolling Mill (1,50,000 TPA) — withdrawn, 0 m away
- Integrated Steel Plant — withdrawn, 0 m away
- Proposed Increase in Production Capacity of Existing Rolling Mill Capacity… — initial checks, 100 m away
- Proposed "increase in Production Capacity of Existing Ferro Alloy From 44,000… — initial checks, 450 m away
- Proposed Up Gradation of existing Induction Furnaces of 2 x 8T to 2 x 10T &… — initial checks, 650 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 650 m away
- Expansion of Integrated Steel Complex — lapsed, 650 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 650 m away
More from Mivaan Steels Limited in Raipur
- Proposed Up Gradation of existing Induction Furnaces of 2 x 8T to 2 x 10T &… — initial checks
- Expansion of Integrated Steel Complex — environmental approval granted
- Proposed "increase in Production Capacity of Existing Ferro Alloy From 44,000… — initial checks
- Proposed Increase in Production Capacity of Existing Rolling Mill Capacity… — initial checks
5 Mivaan Steels projects in Raipur
All 8 Mivaan Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.