Quick answers
What is this project?
Proposed Increase in Production Capacity of Existing Rolling Mill Capacity From 1,50,000 Tpa to 2,40,000 Tpa Without Increase in the Pollution Load in the Existing Plant Premises As Per Gazette Notification Dated 23rd November 2016 & 16th January, 2020 & 2nd March 2021 Issued by Ministry of Environment, Forest & Climate Change is a proposed industrial project in Kurud-I (Kurud), Arang, Raipur, Chhattisgarh. The site covers 5.5 acres.
Who is building it?
The applicant is Mivaan Steels Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Kurud-I (Kurud), Arang, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹35.3 crore and a site of 5.5 acres.
When was it filed?
The application was filed on 21 Mar 2024.
Project details
| Status | Initial checks |
|---|---|
| Status since | 21 Mar 2024 |
| Application filed | 21 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Mivaan Steels Limited |
| Land area | 5.5 acres (2.2 ha) |
| Project cost | ₹35.3 crore |
| Village / locality | Kurud-I (Kurud) |
| Taluk / tehsil | Arang |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01385 |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 5.5 acres, this one is smaller than 73% of them.
137 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kurud-I (Kurud), Arang, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rolling Mill (1,50,000 TPA) in the existing Integrated Steel Plant at Monnet… — environmental approval granted, 100 m away
- Establishment of Rolling Mill (1,50,000 TPA) — withdrawn, 100 m away
- Integrated Steel Plant — withdrawn, 100 m away
- Proposed "increase in Production Capacity of Existing Ferro Alloy From 44,000… — initial checks, 400 m away
- Proposed Up Gradation of existing Induction Furnaces of 2 x 8T to 2 x 10T &… — initial checks, 600 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 600 m away
- Expansion of Integrated Steel Complex — lapsed, 600 m away
- Expansion of Integrated Steel Complex — environmental approval granted, 600 m away
More from Mivaan Steels Limited in Raipur
- Proposed Up Gradation of existing Induction Furnaces of 2 x 8T to 2 x 10T &… — initial checks
- Expansion of Integrated Steel Complex — environmental approval granted
- Proposed "increase in Production Capacity of Existing Ferro Alloy From 44,000… — initial checks
- Rolling Mill (1,50,000 TPA) in the existing Integrated Steel Plant at Monnet… — environmental approval granted
5 Mivaan Steels projects in Raipur
All 8 Mivaan Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.