Quick answers
What is this project?
Proposed Steel Plant (Green Field) with 8 × 650 TPD DRI Kilns-Sponge Iron (17,16,000 TPA), 1 × 65T Electric Arc Furnace (5,40,000 TPA) is a proposed industrial project in Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The site covers 247.7 acres.
Who is building it?
The applicant is Finecrafts Steel and Power Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 16 Feb 2026), as of 27 Nov 2026.
Where is it?
In Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra.
How big is it?
It has a stated cost of ₹5,489 crore and a site of 247.7 acres.
When was it filed?
The application was filed on 16 Feb 2026.
Project details
| Official title | Establishment of Proposed Steel Plant (Green Field) with 8 × 650 TPD DRI Kilns-Sponge Iron (17,16,000 TPA), 1 × 65T Electric Arc Furnace (5,40,000 TPA) along with 1 × 65T LRF, 1 × 4-Strand Billet Caster (5,24,000 TPA), Rolling Mill (Bar & Rod Mill 5,00,000 TPA) And with 6 × 30T Induction Furnaces, 2 × 30T LRFs, 2 × 3-Strand Billet Casters, and Rolling Mill (Light Medium Structural Mill 5, 00,000 TPA), WHRB based Power Plant 4x35MW and AFBC based Power Plant 2x 35 MW |
|---|---|
| Status | Cleared for impact study |
| Status since | 16 Feb 2026 |
| Application filed | 16 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Finecrafts Steel and Power Private Limited |
| Land area | 247.7 acres (100.2 ha) |
| Project cost | ₹5,489 crore |
| Village / locality | Mudholi Chak No.2 |
| Taluk / tehsil | Chamorshi |
| District | Gadchiroli |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-11432 |
In context
30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 247.7 acres, this one is smaller than 63% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction… — environmental approval granted, 1.2 km away
- 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction… — cleared for impact study, 1.2 km away
- Proposed 0.9 MTPA Steel Plant comprising 0.693 MTPA DRI (6x350 TPA DRI Kiln),… — cleared for impact study, 1.7 km away
- Proposed DRI based ISP to manufacture 0.5 MTPA of TMT Rebars comprising 0.825… — cleared for impact study, 2.4 km away
- Proposed 1.8 MTPA Integrated Plant (0.9 MTPA DRI Plant (6x450 TPD) and 0.9… — under environmental review, 2.6 km away
- Proposed 1.8 MTPA Integrated Plant (0.9 MTPA DRI Plant (6x450 TPD) & 0.9 MTPA… — returned to applicant, 2.7 km away
- Proposed Greenfield 3.0 MTPA Integrated Steel Plant (1x1.5 MTPA Coke Oven… — cleared for impact study, 2.8 km away
- Proposed 1.2 MTPA Integrated Steel Plant at Survey Nos. 2, 3, 4, 5, 6 & Others… — under environmental review, 3.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.