Quick answers
What is this project?
Proposed 0.9 MTPA Steel Plant comprising 0.693 MTPA DRI (6x350 TPA DRI Kiln), Steel Making Facility; (6x30T IF, 2x30 T LRFs, 2x2 Strand CCM producing 0.58 MTPA Billets; 1x40T EAF, 1x40T LRF, 1x2 strand CCM producing 0.35 MTPA Billets), Rolling Mill producing 0.56 MTPA TMT Bars, Structural Mill & 0.34 MTPA TMT Bars & Wire Rods, 1x9MVA Submerged Arc Furnace & 68 MW Captive power Plant (48MW WHRB + 20MW AFBC) is a proposed industrial project in Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The site covers 268.8 acres.
Who is building it?
The applicant is Shri Kashi Vishwanath Alloys Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 13 May 2026), as of 27 Nov 2026.
Where is it?
In Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra.
How big is it?
It has a stated cost of ₹1,600 crore and a site of 268.8 acres.
When was it filed?
The application was filed on 11 May 2026.
Project details
| Official title | Establishment of Proposed 0.9 MTPA Steel Plant comprising 0.693 MTPA DRI (6x350 TPA DRI Kiln), Steel Making Facility; (6x30T IF, 2x30 T LRFs, 2x2 Strand CCM producing 0.58 MTPA Billets; 1x40T EAF, 1x40T LRF, 1x2 strand CCM producing 0.35 MTPA Billets), Rolling Mill producing 0.56 MTPA TMT Bars, Structural Mill & 0.34 MTPA TMT Bars & Wire Rods, 1x9MVA Submerged Arc Furnace & 68 MW Captive power Plant (48MW WHRB + 20MW AFBC) at Village Mudholi Chak No. 2, Taluka Chamarshi, District Gadchiroli |
|---|---|
| Status | Cleared for impact study |
| Status since | 13 May 2026 |
| Application filed | 11 May 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shri Kashi Vishwanath Alloys Private Limited |
| Land area | 268.8 acres (108.8 ha) |
| Project cost | ₹1,600 crore |
| Village / locality | Mudholi Chak No.2 |
| Taluk / tehsil | Chamorshi |
| District | Gadchiroli |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-11857 |
In context
30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 268.8 acres, this one is smaller than 60% of them.
21 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed DRI based ISP to manufacture 0.5 MTPA of TMT Rebars comprising 0.825… — cleared for impact study, 700 m away
- 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction… — environmental approval granted, 1.1 km away
- 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction… — cleared for impact study, 1.1 km away
- Proposed Greenfield 3.0 MTPA Integrated Steel Plant (1x1.5 MTPA Coke Oven… — cleared for impact study, 1.2 km away
- Proposed Steel Plant (Green Field) with 8 × 650 TPD DRI Kilns-Sponge Iron… — cleared for impact study, 1.7 km away
- Proposed Diversion of Forest Land Over 13.726 Ha for Proposed Railway Line and… — not approved, 2.6 km away
- Forest Diversion Proposal Over 39.864 Ha of Forest Land for Optimum and… — more information requested, 3.9 km away
- Environmental Clearance for Proposed River Bed Sand Mining Having Leases Area… — environmental approval granted, 3.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.