Quick answers
What is this project?
3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction Furnace, 80 T (6,66,000 TPA) EAF, 6,00,000 TPA Rolling Mill (HBR), 3,00,000 TPA Rolling Mill (RHF), 3,60,000 TPA Flat Product Rolling Mill, 3,00,000 TPA Section Rolling Mill, 1,00,000 TPA Forging, Pickling, Bright Bar, 1,00,000 TPA Ingot Casting & 40 MW WHRB, 40 MW (AFBC) Thermal Power Plant and 4x9MVA Submerged Arc Furnace by Varad Ferro Alloys Private Limited is an approved industrial project in Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The site covers 195 acres.
Who is building it?
The applicant is Varad Ferro-Alloys Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 19 Aug 2026), as of 27 Nov 2026.
Where is it?
In Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra.
How big is it?
It has a stated cost of ₹2,500 crore and a site of 195 acres.
When was it filed?
The application was filed on 30 Jun 2026.
Project details
| Official title | Proposed Installation of 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction Furnace, 80 T (6,66,000 TPA) EAF, 6,00,000 TPA Rolling Mill (HBR), 3,00,000 TPA Rolling Mill (RHF), 3,60,000 TPA Flat Product Rolling Mill, 3,00,000 TPA Section Rolling Mill, 1,00,000 TPA Forging, Pickling, Bright Bar, 1,00,000 TPA Ingot Casting & 40 MW WHRB, 40 MW (AFBC) Thermal Power Plant and 4x9MVA Submerged Arc Furnace by Varad Ferro Alloys Private Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 19 Aug 2026 |
| Application filed | 30 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Varad Ferro-Alloys Private Limited |
| Land area | 195 acres (78.9 ha) |
| Project cost | ₹2,500 crore |
| Village / locality | Mudholi Chak No.2 |
| Taluk / tehsil | Chamorshi |
| District | Gadchiroli |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12182 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 30 Jun 2026 (this page) | Environmental approval granted | 195 acres | ₹2,500 crore |
| Early planning filed 30 Oct 2024 | Cleared for impact study | 195 acres | ₹2,500 crore |
In context
30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 195 acres, this one is smaller than 73% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mudholi Chak No.2, Chamorshi, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 3 x 600 TPD (6,12,000 TPA) Sponge Iron Plant, 8x25 T (6,66,000 TPA) Induction… — cleared for impact study, 0 m away
- Proposed 0.9 MTPA Steel Plant comprising 0.693 MTPA DRI (6x350 TPA DRI Kiln),… — cleared for impact study, 1.1 km away
- Proposed Steel Plant (Green Field) with 8 × 650 TPD DRI Kilns-Sponge Iron… — cleared for impact study, 1.2 km away
- Proposed DRI based ISP to manufacture 0.5 MTPA of TMT Rebars comprising 0.825… — cleared for impact study, 1.6 km away
- Proposed Greenfield 3.0 MTPA Integrated Steel Plant (1x1.5 MTPA Coke Oven… — cleared for impact study, 1.8 km away
- Proposed 1.8 MTPA Integrated Plant (0.9 MTPA DRI Plant (6x450 TPD) & 0.9 MTPA… — returned to applicant, 3 km away
- Proposed 1.8 MTPA Integrated Plant (0.9 MTPA DRI Plant (6x450 TPD) and 0.9… — under environmental review, 3 km away
- Proposed Diversion of Forest Land Over 13.726 Ha for Proposed Railway Line and… — not approved, 3.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.