What is this project?
Tirodi Manganese Ore Mining Project (ML area 254.593 ha) and expansion in production from existing 0.109 MTPA to 0.2 MTPA manganese through opencast mining and dump rehandling. by M/s MOIL limited, at Villages Tirodi & Jamrapani, Tehsil Katangi, District Balaghat, Madhya Pradesh is a proposed mining project in Tirodi, Balaghat, Madhya Pradesh. The site covers 629.1 acres.
Who is building it?
The applicant is Vikash Parida.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 14 Nov 2023), as of 27 Nov 2026.
Where is it?
In Tirodi, Balaghat, Madhya Pradesh.
How big is it?
It has a stated cost of ₹79.2 crore and a site of 629.1 acres.
When was it filed?
The application was filed on 4 Aug 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 14 Nov 2023 |
| Application filed | 4 Aug 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Vikash Parida |
| Land area | 629.1 acres (254.6 ha) |
| Project cost | ₹79.2 crore |
| Village / locality | Tirodi |
| Taluk / tehsil | Tirodi |
| District | Balaghat |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-02192 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 31 Oct 2026 | Under environmental review | 629.1 acres | ₹79.2 crore |
| Expansion filed 31 Oct 2026 | More information requested | 629.1 acres | ₹79.2 crore |
| Early planning filed 4 Aug 2023 (this page) | Cleared for impact study | 629.1 acres | ₹79.2 crore |
In context
204 applications in Balaghat since January 2022 are in the same category (Mining): 113 approved, 51 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 29 days from filing to approval. At 629.1 acres, this one is larger than 97% of them.
No other mining lease on record is within 500 m of this site; 5 have applied within 5 km.
Where it is
Tirodi, Balaghat, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Tirodi Manganese Ore Mining Project (ML area 254.593 ha) and expansion in… — under environmental review, 0 m away
- Tirodi Manganese Ore Mining Project (ML area 254.593 ha) and expansion in… — more information requested, 0 m away
- Expansion of Tirodi Manganese Ore Mine From Production Capacity of 3700 Tpa to… — under environmental review, 800 m away
- Transfer of Environmental Clearance of Tirodi Manganese Ore Mining Project — environmental approval granted, 850 m away
- Proposed Mining of Manganese (Major Mineral), with maximum production capacity… — environmental approval granted, 950 m away
- Submersible bridge across Doriya Nalla on Kharpadiya - Shivanheti Road In… — lapsed, 2.2 km away
- MOIL Limited-Tirodi Mine-Forest Land — lapsed, 3 km away
- Sonegaon Manganese ore mine (4.998ha) with production capacity of ROM-11774TPA… — environmental approval granted, 4.6 km away
More from Vikash Parida in Balaghat
- Kanki Sand Mining Lease of MOIL Limited over an area of 4.413 Ha, at Khasra… — lapsed
- MOIL-Sukli Forest for Drilling — forest land use approved
- Kanki Sand Mining Lease of MOIL Limited over an area of 4.413 Ha, at Khasra… — lapsed
- Kanki Sand Mining Lease of MOIL Limited over an area of 4.413 Ha, at Khasra… — cleared for impact study
- Ukwa Mine Project. — more information requested
- MOIL Limited-Tirodi Mine-Forest Land — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.