Cleared for impact studyMining · Balaghat, Madhya Pradesh

Expansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000 Tpa in an Area of 73.567 Ha

Expansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000 Tpa in an Area of 73.567 Ha is a proposed mining project in Ukwa (Ct), Paraswada, Balaghat, Madhya Pradesh. The site covers 181.8 acres. Its stated project cost is ₹269 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 6 Aug 2026).

See it on the live map All projects in Balaghat

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000 Tpa in an Area of 73.567 Ha is a proposed mining project in Ukwa (Ct), Paraswada, Balaghat, Madhya Pradesh. The site covers 181.8 acres.

Who is building it?

The applicant is Moil Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 6 Aug 2026), as of 27 Nov 2026.

Where is it?

In Ukwa (Ct), Paraswada, Balaghat, Madhya Pradesh.

How big is it?

It has a stated cost of ₹269 crore and a site of 181.8 acres.

When was it filed?

The application was filed on 5 Mar 2026.

Project details

Official titleExpansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000 Tpa in an Area of 73.567 Ha at Lugma & Ukwa Village, Paraswara Tehsil, Balaghat District, Madhya Pradesh
StatusCleared for impact study
Status since6 Aug 2026
Application filed5 Mar 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantMoil Limited
Land area181.8 acres (73.6 ha)
Project cost₹269 crore
Village / localityUkwa (Ct)
Taluk / tehsilParaswada
DistrictBalaghat
StateMadhya Pradesh
Location fromSite boundary on record
Our referenceWID-MP-08262

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 7 Oct 2026Under environmental review181.8 acres₹269 crore
Early planning filed 5 Mar 2026 (this page)Cleared for impact study181.8 acres₹269 crore

In context

204 applications in Balaghat since January 2022 are in the same category (Mining): 113 approved, 51 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 29 days from filing to approval. At 181.8 acres, this one is larger than 92% of them.

3 other mining leases have applied within 500 m of this site; together with this one they cover 938.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.

Where it is

Ukwa (Ct), Paraswada, Balaghat, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Moil Limited in Balaghat

10 Moil projects in Balaghat
All 25 Moil projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.