Quick answers
What is this project?
Expansion of Manganese Mines From Production Capacity of 17000 Tpa to 70000 Tpa in an Area of 43.353 Ha is a proposed mining project in Sukli, Tirodi, Balaghat, Madhya Pradesh. The site covers 107.1 acres.
Who is building it?
The applicant is Moil Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 8 Nov 2023), as of 27 Nov 2026.
Where is it?
In Sukli, Tirodi, Balaghat, Madhya Pradesh.
How big is it?
It has a stated cost of ₹8.7 crore and a site of 107.1 acres.
When was it filed?
The application was filed on 8 Nov 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Manganese Mines From Production Capacity of 17000 Tpa to 70000 Tpa in an…
Project details
| Official title | Expansion of Manganese Mines From Production Capacity of 17000 Tpa to 70000 Tpa in an Area of 43.353 Ha at Sitapathore Village, Tirodi Tehsil, Balaghat District, Madhya Pradesh |
|---|---|
| Status | Cleared for impact study |
| Status since | 8 Nov 2023 |
| Application filed | 8 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Moil Limited |
| Land area | 107.1 acres (43.4 ha) |
| Project cost | ₹8.7 crore |
| Village / locality | Sukli |
| Taluk / tehsil | Tirodi |
| District | Balaghat |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-00572 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 12 Jan 2025 | Environmental approval granted | 107.1 acres | ₹8.7 crore |
| Early planning filed 8 Nov 2023 (this page) | Cleared for impact study | 107.1 acres | ₹8.7 crore |
In context
204 applications in Balaghat since January 2022 are in the same category (Mining): 113 approved, 51 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 29 days from filing to approval. At 107.1 acres, this one is larger than 87% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 118.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 3 mining leases have applied within 5 km.
Where it is
Sukli, Tirodi, Balaghat, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Manganese Mines From Production Capacity of 17000 Tpa to 70000… — environmental approval granted, 0 m away
- Mining of Manganese (Major Mineral), With Production Capacity of 200 Tpa Over… — environmental approval granted, 300 m away
- MOIL-Sukli Forest for Drilling — forest land use approved, 950 m away
- Preliminary investigation for Manganese in Sausar Group of rocks in Kharpariya… — forest land use approved, 1.1 km away
- Sitapathore exploration Block — forest land use approved, 1.7 km away
- Sitapathore Mangnese Ore Quarry — environmental approval granted, 2 km away
- Sukli Block-B Manganese Ore — forest land use approved, 2.3 km away
- GENERAL EXPLORATION (G-2 STAGE) FOR MANGANESE AND ASSOCIATED MINERALS IN SUKLI… — more information requested, 2.7 km away
More from Moil Limited in Balaghat
- Expansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000… — under environmental review
- Expansion of Tirodi Manganese Ore Mine From Production Capacity of 3700 Tpa to… — under environmental review
- Expansion of Manganese Mines From Production Capacity of 1,20,000 to 2,16,000… — cleared for impact study
- Proposed Expansion of Balaghat Manganese Ore Mining and Beneficiation plant… — under environmental review
- Proposed Expansion of Balaghat Manganese Ore Mining and Beneficiation plant… — cleared for impact study
- Expansion of Manganese Mines From Production Capacity of 1,20,000 Tpa to… — cleared for impact study
10 Moil projects in Balaghat
All 25 Moil projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.