Capacity Enhancement of Existing Hot Rolling Mill Capacity From 52,000 Tpa to 61,470 Tpa With Same Plant & Machinery Within Same Premises Based on No Increase in Pollution Load As Per 7(II) of Eia Notification 2006 at Msp Sponge Iron LTD., Haldiaguna, Keonjhar, Odisha by Process Upgradation Involving Increase of Mill Operation Hour From 15 to 18 Hours / Day is a proposed industrial project in Bannamaruni, Kendujhar Sadar, Kendujhar, Odisha. The site covers 74.2 acres.
Who is building it?
The applicant is Msp Sponge Iron Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Bannamaruni, Kendujhar Sadar, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹378.6 crore and a site of 74.2 acres.
When was it filed?
The application was filed on 26 Sept 2025.
Project details
| Official title | Proposal for Capacity Enhancement of Existing Hot Rolling Mill Capacity From 52,000 Tpa to 61,470 Tpa With Same Plant & Machinery Within Same Premises Based on No Increase in Pollution Load As Per 7(II) of Eia Notification 2006 at Msp Sponge Iron LTD., Haldiaguna, Keonjhar, Odisha by Process Upgradation Involving Increase of Mill Operation Hour From 15 to 18 Hours / Day. |
|---|---|
| Status | Initial checks |
| Status since | 26 Sept 2025 |
| Application filed | 26 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Msp Sponge Iron Limited |
| Land area | 74.2 acres (30 ha) |
| Project cost | ₹378.6 crore |
| Village / locality | Bannamaruni |
| Taluk / tehsil | Kendujhar Sadar |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03147 |
In context
38 applications in Kendujhar since January 2022 are in the same category (Industry): 9 approved, 12 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 74.2 acres, this one is smaller than 63% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bannamaruni, Kendujhar Sadar, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed for Enhancement of Production Capacity and Change in Configuration of… — initial checks, 0 m away
- Expansion of existing Integrated steel plant to final capacity of Iron Ore… — lapsed, 100 m away
- Expansion of existing Integrated steel plant to final capacity of Iron Ore… — cleared for impact study, 100 m away
- Proposed Enhancement of Production Capacity of (2 × 100 Tpd) Dri From 60,000… — initial checks, 2.7 km away
- Amendment & Extension of validity of ToR by addition of "a slag crusher unit… — lapsed, 4.7 km away
- Name Change (Transfer) of the Environment Clearance (EC File no.… — lapsed, 4.8 km away
- Expansion of existing Facility of Sponge iron from 2,60,000 TPA to 11,18,000… — lapsed, 4.8 km away
- Transfer of Environment Clearance of Tikarapada Stone Quarry-1 Over an Area of… — environmental approval granted, 8.3 km away
More from Msp Sponge Iron Limited in Kendujhar
- Expansion of existing Integrated steel plant to final capacity of Iron Ore… — lapsed
- Expansion of existing Integrated steel plant to final capacity of Iron Ore… — cleared for impact study
All 3 Msp Sponge Iron projects across India