Quick answers
What is this project?
Expansion of Talcher Thermal Power Project from existing 1320 MW (Stage-III: 2x660 MW) to 2120 MW by addition of Stage-IV (1x800 MW) Ultra Super Critical Technology Coal Based Power Plant at Gram panchayat- Santaparha, Jagannathpur, Bantol, & Gurujanguli at Talcher by NTPC is a proposed power project in Remua, Colliery, Anugul, Odisha. The site covers 551.5 acres.
Who is building it?
The applicant is NTPC Limited (NTPC).
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Remua, Colliery, Anugul, Odisha.
How big is it?
It has a stated cost of ₹24,221 crore and a site of 551.5 acres.
When was it filed?
The application was filed on 5 May 2026.
Project details
| Official title | Expansion of Talcher Thermal Power Project from existing 1320 MW (Stage-III: 2x660 MW) to 2120 MW by addition of Stage-IV (1x800 MW) Ultra Super Critical Technology Coal Based Power Plant at Gram panchayat- Santaparha, Jagannathpur, Bantol, & Gurujanguli at Talcher in Tehsil Talcher Sadar, Angul District, Odisha by NTPC Limited |
|---|---|
| Status | Under environmental review |
| Status since | 13 Jun 2026 |
| Application filed | 5 May 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Power |
| Applicant | NTPC Limited (NTPC) |
| Land area | 551.5 acres (223.2 ha) |
| Project cost | ₹24,221 crore |
| Village / locality | Remua |
| Taluk / tehsil | Colliery |
| District | Anugul |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03710 |
In context
17 applications in Anugul since January 2022 are in the same category (Power): 7 approved, 9 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 551.5 acres, this one is smaller than 75% of them.
11 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Remua, Colliery, Anugul, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 2x660 MW (Stage-III, Expansion) Coal based Ultra Super Critical Talcher… — environmental approval granted, 1.3 km away
- Dhobapal Sand Quarry over an area of 18.00 acres or 7.28 Hectares bearing… — not approved, 1.9 km away
- Application for Amendment of Ec for Mining of Sand From Nizagarhzami Sand… — environmental approval granted, 2.2 km away
- Application for Amendment of Ec for Mining of Sand From Nizagarhzami Sand… — not approved, 2.2 km away
- Proposed Intake Water Pipeline Corridor for Ttps Expansion Project(2 X 660MW)… — forest land use approved, 2.6 km away
- Environmental Clearance for production of 9000 Cum/annum of River Sand over… — initial checks, 3 km away
- Environmental Clearance for production of 9000 Cum/annum of River Sand over… — returned to applicant, 3 km away
- Environmental Clearance for production of 9000 Cum/annum of River Sand over… — environmental approval granted, 3 km away
More from NTPC Limited (NTPC) in Anugul
- 2x660 MW (Stage-III, Expansion) Coal based Ultra Super Critical Talcher… — environmental approval granted
- Proposed Intake Water Pipeline Corridor for Ttps Expansion Project(2 X 660MW)… — forest land use approved
3 NTPC projects in Anugul
All 129 NTPC projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.