Mirpur Durg RBM Mining Project, Proponent Team Growth Private Limited, Prateek Pramod Bhatnagar. Gata No. 183, Village Mirpur Durg, Tehsil Najibabad, District Bijnor Uttar Pradesh, Area 1.078 ha is an approved mining project in Mirpur Dargu, Najibabad, Bijnor, Uttar Pradesh. The site covers 2.7 acres.
Who is building it?
The applicant is Prateek Pramod Bhatnagar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 17 Jan 2026), as of 27 Nov 2026.
Where is it?
In Mirpur Dargu, Najibabad, Bijnor, Uttar Pradesh.
How big is it?
It has a stated cost of ₹20 lakh and a site of 2.7 acres.
When was it filed?
The application was filed on 15 May 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 17 Jan 2026 |
| Application filed | 15 May 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Prateek Pramod Bhatnagar |
| Land area | 2.7 acres (1.1 ha) |
| Project cost | ₹20 lakh |
| Village / locality | Mirpur Dargu |
| Taluk / tehsil | Najibabad |
| District | Bijnor |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-02609 |
In context
24 applications in Bijnor since January 2022 are in the same category (Mining): 15 approved, 9 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.7 acres, this one is smaller than 92% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Mirpur Dargu, Najibabad, Bijnor, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed forest land to be diverted for Entry/Exit approach to BPCL Retail… — lapsed, 3.8 km away
- "R.B.M. (In mix form) Mining" Project at Gata No.- 413, 414, 221, 222, 223,… — environmental approval granted, 4.1 km away
- "Proposed Project of Mining of RBM (Mixed form) on Riverbed of Malin River"… — environmental approval granted, 5.5 km away
- Proposed Protected Forest Land to be diverted for Entry/Exit approach to M/s… — more information requested, 6 km away
- Ordinary Soil Mine — initial checks, 8.7 km away
- Sundarwali Sand Mining Project, Located on river bed of Khoh River (1.960 ha) — environmental approval granted, 10.6 km away
- Proposed Project of "Sand- Bajri-Boulders in Mixed State (RBM) Mine" located… — environmental approval granted, 11.2 km away
- Proposed Project of "Sand- Bajri-Boulders in Mixed State (RBM) Mine" located… — cleared for impact study, 11.2 km away
More from Prateek Pramod Bhatnagar in Bijnor
- "RBM (Mixed Form)" at Gata No. 2/102, Area- 1.215 Ha, Village- Shah Alipur… — environmental approval granted
- "Proposed Project of Mining of RBM (Mixed form) on Riverbed of Malin River"… — environmental approval granted
About this information