Quick answers
What is this project?
"Sand/Morrum Mine" from Riverbed of Dhasan River, Village- Gadhar, Gata No.- 01, 23/2, Khand No.- 02, Lease area- 26.00 Ha., Tehsil- Rath, District- Hamirpur, Uttar Pradesh, Project Proponent- M/s Satyaom Developers Pvt. Ltd. (Director- Shri Satyaprakash Gupta) is a proposed mining project in Gokal, Garautha, Jhansi, Uttar Pradesh. The site covers 64.2 acres.
Who is building it?
The applicant is Satyaom Developers Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Gokal, Garautha, Jhansi, Uttar Pradesh.
How big is it?
It has a stated cost of ₹44.3 crore and a site of 64.2 acres.
When was it filed?
The application was filed on 27 May 2025.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 4 Sept 2026 |
| Application filed | 27 May 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Satyaom Developers Private Limited |
| Land area | 64.2 acres (26 ha) |
| Project cost | ₹44.3 crore |
| Village / locality | Gokal |
| Taluk / tehsil | Garautha |
| District | Jhansi |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-03749 |
In context
211 applications in Jhansi since January 2022 are in the same category (Mining): 146 approved, 39 filed or under review, and 26 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 64.2 acres, this one is larger than 98% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 113.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 6 mining leases have applied within 5 km.
Where it is
Gokal, Garautha, Jhansi, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed "Morrum" Mine Project at Gata No.- 908Na (Khand- 02), Village-… — under environmental review, 350 m away
- Kharwanch Sand/Morrum Mining Project on Dhasan River — cleared for impact study, 750 m away
- Kharwanch Sand/Morrum Mining Project on Dhasan River — environmental approval granted, 750 m away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of River… — environmental approval granted, 2 km away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of River… — cleared for impact study, 2 km away
- Proposed project of Riverbed Sand/Morrum Mining from Riverbed of Dhasan River… — under environmental review, 3.2 km away
- Proposed project of Riverbed Sand/Morrum Mining from Riverbed of Dhasan River… — cleared for impact study, 3.2 km away
- Environmental Clearance for Proposed Sand/Morrum Mining from Dhasan Riverbed… — lapsed, 4 km away
All 3 Satyaom Developers projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.