Environmental Clearance for the Proposed Aluminium Can Manufacturing Unit at Plot no. - 4, UPEIDA IMLC Unnao, Village- Sarai Katiyan, Tehsil -Sadar, District – Unnao, Uttar Pradesh, India by Crown Packaging India Private Limited is a proposed building project in Sarai Katian, Unnao, Uttar Pradesh. The site covers 40.1 acres.
Who is building it?
The applicant is Crown Packaging India Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Sarai Katian, Unnao, Uttar Pradesh.
How big is it?
It has a stated cost of ₹2,163 crore and a site of 40.1 acres.
When was it filed?
The application was filed on 16 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 18 Nov 2026 |
| Application filed | 16 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Crown Packaging India Private Limited |
| Land area | 40.1 acres (16.2 ha) |
| Project cost | ₹2,163 crore |
| Village / locality | Sarai Katian |
| Taluk / tehsil | Unnao |
| District | Unnao |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-04938 |
In context
28 applications in Unnao since January 2022 are in the same category (Buildings & townships): 12 approved, 7 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 40.1 acres, this one is larger than 50% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sarai Katian, Unnao, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 1.3 MHLPA (Million Hectolitres per Annum)Brewery Project Located at… — under environmental review, 400 m away
- Proposed 1.3 MHLPA (Million Hectolitres per Annum)Brewery Project Located at… — environmental approval granted, 400 m away
- Proposed Integrated Manufacturing and Logistic Cluster (IMLC) Unnao — environmental approval granted, 500 m away
- Proposed Integrated Manufacturing and Logistic Cluster (IMLC) Unnao — cleared for impact study, 500 m away
- Proposed Integrated Manufacturing and Logistic Cluster (IMLC) Unnao — returned to applicant, 500 m away
- Proposed industrial shed for Manufacturing of Aluminium Beverage Cans by M/s.… — environmental approval granted, 1.1 km away
- Improvement and Rectification work of 05 nos. of MoRTH Identified Black Spot… — in-principle approval, conditions pending, 3.5 km away