In-principle approval, conditions pendingRoads & highways · Unnao, Uttar Pradesh

Improvement and Rectification work of 05 nos. of MoRTH Identified Black Spot Location through long term measures on Lucknow Kanpur Section of Old NH-25 (New NH-27) (Km 27 700 to Km 75 500) in the State of UP- Diversion of 3.025 Ha. Protected Forest Land under Social Forestry Division, Unnao for construction of Underpass & Junction Improvement for 05 Nos. of separate Blackspot Locations.

Improvement and Rectification work of 05 nos. of MoRTH Identified Black Spot Location through long term measures on Lucknow Kanpur Section of Old NH-25 (New NH-27) (Km 27 700 to Km 75 500) in the State of UP- Diversion of 3.025 Ha. Protected Forest Land under Social Forestry Division, Unnao for construction of Underpass & Junction Improvement for 05 Nos. of separate Blackspot Locations is a proposed road project in Chamrauli, Hasanganj, Unnao, Uttar Pradesh. The site covers 43 acres. Its stated project cost is ₹136.8 crore. As of 27 Nov 2026, its status is “In-principle approval, conditions pending” (since 30 Sept 2026).

See it on the live map All projects in Unnao

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Improvement and Rectification work of 05 nos. of MoRTH Identified Black Spot Location through long term measures on Lucknow Kanpur Section of Old NH-25 (New NH-27) (Km 27 700 to Km 75 500) in the State of UP- Diversion of 3.025 Ha. Protected Forest Land under Social Forestry Division, Unnao for construction of Underpass & Junction Improvement for 05 Nos. of separate Blackspot Locations is a proposed road project in Chamrauli, Hasanganj, Unnao, Uttar Pradesh. The site covers 43 acres.

Who is building it?

The applicant is National Highway Authority of India.

Has it been approved?

Not yet. The application is still under review: its status is “In-principle approval, conditions pending”, as of 27 Nov 2026.

Where is it?

In Chamrauli, Hasanganj, Unnao, Uttar Pradesh.

How big is it?

It has a stated cost of ₹136.8 crore; a site of 43 acres and 7.5 acres (3 ha) of forest land.

When was it filed?

The application was filed on 1 Dec 2025.

Project details

StatusIn-principle approval, conditions pending
Status since30 Sept 2026
Application filed1 Dec 2025
Approval soughtForest land use
Application typeNew project
SectorRoads & highways
ApplicantNational Highway Authority of India
Land area43 acres (17.4 ha)
Forest land7.5 acres (3 ha)
Project cost₹136.8 crore
Village / localityChamrauli
Taluk / tehsilHasanganj
DistrictUnnao
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-05651

In context

7 applications in Unnao since January 2022 are in the same category (Roads & highways): 2 approved, 3 filed or under review, and 2 withdrawn, lapsed or rejected.

11 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Chamrauli, Hasanganj, Unnao, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 548 National Highways Authority of India (NHAI) projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.