Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail Outlet is an approved fuel station in Mazra, Tanda, Rampur, Uttar Pradesh. The site covers 0.7 acres.
Who is building it?
The applicant is Indian Oil Corporation Limited (IOCL).
Has it been approved?
Yes. Its status is “Forest land use approved” (since 7 Nov 2024), as of 27 Nov 2026.
Where is it?
In Mazra, Tanda, Rampur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹60 lakh; a site of 0.7 acres and 1,480 m² of forest land.
When was it filed?
The application was filed on 7 Jul 2024.
Project details
| Official title | Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail Outlet at Village:-Sandu ka majra, Tehsil:-Tanda, District:-Rampur. |
|---|---|
| Status | Forest land use approved |
| Status since | 7 Nov 2024 |
| Application filed | 7 Jul 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Fuel stations |
| Applicant | Indian Oil Corporation Limited (IOCL) |
| Land area | 2,700 m² |
| Forest land | 1,480 m² |
| Project cost | ₹60 lakh |
| Village / locality | Mazra |
| Taluk / tehsil | Tanda |
| District | Rampur |
| State | Uttar Pradesh |
| Location from | Site area on record |
| Our reference | WID-UP-05732 |
In context
30 applications in Rampur since January 2022 are in the same category (Fuel stations): 21 approved, 4 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 0.7 acres, this one is smaller than 80% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mazra, Tanda, Rampur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- High Speed Access Controlled Corridor from Shamli - Gorakhpur (Phase-I) in the… — returned to applicant, 4.5 km away
- High Speed Access Controlled Corridor from Shamli - Gorakhpur (Phase-I) in the… — cleared for impact study, 4.5 km away
- Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail… — initial checks, 6.4 km away
- Proposed Protected Forest Land to be Diverted for Entry/Exit approach to… — lapsed, 6.7 km away
- Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail… — forest land use approved, 7.6 km away
- Expansion of existing Sugar unit from 5,000 TCD to 10,000 TCD — environmental approval granted, 8.2 km away
- Expansion of existing Sugar unit from 5,000 TCD to 10,000 TCD — cleared for impact study, 8.2 km away
- High Speed Access Controlled Corridor from Shamli - Gorakhpur (Phase-I) in the… — more information requested, 8.4 km away
More from Indian Oil Corporation Limited (IOCL) in Rampur
- Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL… — more information requested
- Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL… — in-principle approval, conditions pending
- Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL… — forest land use approved
- Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail… — forest land use approved
- Protected Forest Land to be Diverted for Entry/Exit approach to IOCL Retail… — forest land use approved
- Proposed Protected Forest Land to be Diverted for Entry/Exit approach to IOCL… — forest land use approved
13 Indian Oil Corporation (IOCL) projects in Rampur
All 822 Indian Oil Corporation (IOCL) projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.