Quick answers
What is this project?
Environment Clearance (in compliance of the NGT order dt. 12.02.2020 in Original Application No. 55/2019(WZ), for the Rolling Mill of 1,20,000 TPA set up on Consent to Establish Basis at its existing project site at Vill: Ghutgoria, Kadasole, Barjora, Dist: Bankura, West Bengal-722202 is a proposed industrial project in Baikunthapur, Barjora, Bankura, West Bengal. The site covers 4.9 acres.
Who is building it?
The applicant is Surya Alloy Industries Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 23 Nov 2023), as of 27 Nov 2026.
Where is it?
In Baikunthapur, Barjora, Bankura, West Bengal.
How big is it?
It has a stated cost of ₹10 crore and a site of 4.9 acres.
When was it filed?
The application was filed on 23 Nov 2023.
Project details
| Official title | Proposal for Environment Clearance (in compliance of the NGT order dt. 12.02.2020 in Original Application No. 55/2019(WZ), for the Rolling Mill of 1,20,000 TPA set up on Consent to Establish Basis at its existing project site at Vill: Ghutgoria, Kadasole, Barjora, Dist: Bankura, West Bengal-722202 |
|---|---|
| Status | Cleared for impact study |
| Status since | 23 Nov 2023 |
| Application filed | 23 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Surya Alloy Industries Limited |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹10 crore |
| Village / locality | Baikunthapur |
| Taluk / tehsil | Barjora |
| District | Bankura |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00003 |
In context
69 applications in Bankura since January 2022 are in the same category (Industry): 29 approved, 23 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4.9 acres, this one is smaller than 94% of them.
32 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Baikunthapur, Barjora, Bankura, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance (EC) granted by the Ministry of… — returned to applicant, 550 m away
- Transfer of Environmental Clearance (EC) granted by the Ministry of… — returned to applicant, 550 m away
- Proposed expansion project by installation of 4X30 T Induction Furnaces… — environmental approval granted, 950 m away
- Diversion of Forest Land at Mouza-Saharjora (Plasto Steel Park) for Setting of… — not approved, 1 km away
- Industrial project by SBEG Consultants Pvt. Ltd. — lapsed, 1.1 km away
- Expansion of Existing Secondary Metallurgical Unit by Installing Additional… — cleared for impact study, 1.4 km away
- Proposed 0.13 MTPA Ferro Alloys Plant (6 X 9 MVA SAF, 2X6 T EAF, 2X15 T AOD,… — environmental approval granted, 2 km away
- Proposed 0.13 MTPA Ferro Alloys Plant (6 X 9 MVA SAF, 2X6 T EAF, 2X15 T AOD,… — under environmental review, 2.3 km away
More from Surya Alloy Industries Limited in Bankura
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.