Proposed backward integration by establishment of 1 x 500 TPD DRI Kiln to manufacture 1,65,000 TPA is a proposed industrial project in Kirna, Tilda, Raipur, Chhattisgarh. The site covers 42.1 acres.
Who is building it?
The applicant is Shaurya Ispat Udyog Pvt.Ltd..
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 2 Nov 2023), as of 27 Nov 2026.
Where is it?
In Kirna, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹232 crore and a site of 42.1 acres.
When was it filed?
The application was filed on 16 Sept 2023.
Project details
| Official title | Proposed backward integration by establishment of 1 x 500 TPD DRI Kiln to manufacture 1,65,000 TPA along with 1 x 10 MW WHRB Power Plant and 1 x 10 MW FBC Power Plant along with Brick Manufacturing unit (16,000 Bricks / Day) |
|---|---|
| Status | Cleared for impact study |
| Status since | 2 Nov 2023 |
| Application filed | 16 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shaurya Ispat Udyog Pvt.Ltd. |
| Land area | 42.1 acres (17 ha) |
| Project cost | ₹232 crore |
| Village / locality | Kirna |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site area on record |
| Our reference | WID-CG-00725 |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 42.1 acres, this one is larger than 60% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kirna, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield steel plant comprising of Pelletization plant 0.9 MTPA, along Coal… — cleared for impact study, 650 m away
- Proposed expansion in permitted capacities with inclusion of HRAP Steel… — cleared for impact study, 2.8 km away
- Greenfield Steel Plant Comprising of Pellet Plant1x2,000tpd–6,60,000tpa — under environmental review, 2.8 km away
- Expansion of Integrated Steel plant-Sponge Iron Plant-0.6 MTPA,Power Plant-125… — lapsed, 3.3 km away
- Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA… — environmental approval granted, 3.3 km away
- Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA… — cleared for impact study, 3.3 km away
- Green Field Project 2.2 MTPA Integrated Steel Plant at Khasra No. 746, 747,… — more information requested, 3.8 km away
- Transfer of Environment Clearance vide no. IA-J-11011/88/2023-IA-II(IND-I) dt.… — environmental approval granted, 5.4 km away