Quick answers
What is this project?
For proposed "Change in the DRI plant configuration from 2x500 TPD DRI Kilns to 2x350TPD,1x300TPD DRI Kilns and Combined Stack for 2x350TPD DRI Kilns and Combined Stack proposed to 1x300TPD DRI Kiln & FBC Power Plant of 1x10M,& Separate Stack for FBC Power Plant of 1x10MW without increase in the Pollution Load in the existing plant premises as per Gazette Notification dated 23rd November 2016 & 16th January, 2020 & 2nd March 2021 issued by Ministry of Environment, Forest & Climate Change is a proposed power project in Bahesar, Tilda, Raipur, Chhattisgarh. The site covers 30.5 acres.
Who is building it?
The applicant is Shaurya Ispat Udyog Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Bahesar, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹400 crore and a site of 30.5 acres.
When was it filed?
The application was filed on 27 Jul 2024.
Project details
| Status | Initial checks |
|---|---|
| Status since | 27 Jul 2024 |
| Application filed | 27 Jul 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | Shaurya Ispat Udyog Private Limited |
| Land area | 30.5 acres (12.4 ha) |
| Project cost | ₹400 crore |
| Village / locality | Bahesar |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01527 |
In context
13 applications in Raipur since January 2022 are in the same category (Power): 4 approved, 8 filed or under review, and 1 withdrawn, lapsed or rejected. At 30.5 acres, this one is smaller than 92% of them.
28 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bahesar, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield steel plant comprising of DRI Kilns (2 x 500 TPD) – 3,30,000 TPA,… — lapsed, 0 m away
- Request for Amendment to the Environmental Clearance (Ec) to Permit the… — environmental approval granted, 150 m away
- Speciality Chemical Manufacturing Unit — cleared for impact study, 1000 m away
- Pellet plant of 1x 0.3 MTPA (3,00,000TPA)DRI Kilns (Sponge Iron 1,80,000TPA)… — environmental approval granted, 1.7 km away
- Pellet plant of 1x 0.3 MTPA (3,00,000TPA)DRI Kilns (Sponge Iron 1,80,000TPA)… — cleared for impact study, 1.7 km away
- EC – Corrigendum for correction in lease area in EC Name change letter No.… — environmental approval granted, 1.8 km away
- Regularization of Re-Rolling Mill plant of 30,000 MTPA capacity, in compliance… — cleared for impact study, 2.1 km away
- Proposed Change in the DRI plant configuration from 3 x 100 TPD Kilns to 1 x… — initial checks, 2.2 km away
More from Shaurya Ispat Udyog Private Limited in Raipur
- Request for Amendment to the Environmental Clearance (Ec) to Permit the… — environmental approval granted
- Proposed Greenfield steel plant comprising of DRI Kilns (2 x 500 TPD) –… — environmental approval granted
- Proposed Greenfield steel plant comprising of DRI Kilns (2 x 500 TPD) –… — cleared for impact study
- Greenfield steel plant comprising of DRI Kilns (2 x 500 TPD) – 3,30,000 TPA,… — lapsed
All 6 Shaurya Ispat Udyog projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.