Gare Palma IV/6 Coal Mine (4 Mtpa) and Coal Washery (4 Mtpa) in an Ml Area of 381.42 Ha Located at Raigarh, Chhattisgarh is an approved mining project in Gare, Tamnar, Raigarh, Chhattisgarh. The site covers 942.5 acres.
Who is building it?
The applicant is Jindal Steel Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 2 Feb 2026), as of 27 Nov 2026.
Where is it?
In Gare, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹479 crore and a site of 942.5 acres.
When was it filed?
The application was filed on 19 Sept 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 2 Feb 2026 |
| Application filed | 19 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Jindal Steel Limited |
| Land area | 942.5 acres (381.4 ha) |
| Project cost | ₹479 crore |
| Village / locality | Gare |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02863 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 5 Oct 2026 | Under environmental review | 942.5 acres | ₹479 crore |
| Ownership transfer filed 19 Sept 2025 (this page) | Environmental approval granted | 942.5 acres | ₹479 crore |
In context
230 applications in Raigarh since January 2022 are in the same category (Mining): 83 approved, 47 filed or under review, and 100 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 942.5 acres, this one is larger than 78% of them.
No other mining lease on record is within 500 m of this site; 16 have applied within 5 km.
Where it is
Gare, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Gare Palma IV/6 Coal Mine (4 Mtpa) and Coal Washery (4 Mtpa) in an Ml Area of… — under environmental review, 0 m away
- Gare Palma Sector-II Coal Mine Project of 23.60 MTPA (OC-22.0 MTPA + UG- 1.6… — environmental approval granted, 1.8 km away
- Expansion of Karwahi Open cast Coal Mine (Gare Palma IV/7 Coal Mine)… — environmental approval granted, 1.9 km away
- Expansion of Karwahi Open cast Coal Mine (Gare Palma IV/7 Coal Mine)… — lapsed, 1.9 km away
- Expansion of Karwahi Open cast Coal Mine (Gare Palma IV/7 Coal Mine)… — lapsed, 1.9 km away
- Revised EIA/EMP Report as per the provisions under para 7 (ii) (a) EIA… — environmental approval granted, 1.9 km away
- Expansion of Karwahi Open cast Coal Mine (Gore Palma IV/7 Coal Mine)… — environmental approval granted, 2.2 km away
- Diversion of 33.613 Ha Forest Land (33.608 Ha within lease area) and Railway… — more information requested, 2.2 km away
More from Jindal Steel Limited in Raigarh
- Expansion of Existing Integrated Steel Plant From 3.6 Mtpa to 12.6 Mtpa Crude… — under environmental review
- Amendment in Ec for Change in the Project Land of Already Existing Integrated… — lapsed
- Transfer of Environmental Clearance granted for Integrated Steel plant (3.6… — environmental approval granted
- Transfer of Environmental Clearance granted for Cement Plant at Raigarh,… — environmental approval granted
- Application for "No Increase in Pollution Load" Certificate for Expansion of… — initial checks
- 4x150 MW coal based Thermal Power Plant located at Dongamahua, Tehsil-Tamnar,… — environmental approval granted
8 Jindal Steel projects in Raigarh
All 39 Jindal Steel projects across India