What is this project?
Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane Syrup/Grain) based Distillery by M/s. TruAlt Bioenergy Ltd. Unit-IV is an approved industrial project in Jalageri, Badami, Bagalkote, Karnataka. The site covers 28.3 acres.
Who is building it?
The applicant is Trualt Bioenergy Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 1 Aug 2024), as of 27 Nov 2026.
Where is it?
In Jalageri, Badami, Bagalkote, Karnataka.
How big is it?
It has a stated cost of ₹650 crore and a site of 28.3 acres.
When was it filed?
The application was filed on 3 Apr 2024.
Project details
| Official title | Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane Syrup/Grain) based Distillery along with 10 MW Co-generation Power Plant at Village Jalageri, Tehsil Badami, District Bagalkot, Karnataka by M/s. TruAlt Bioenergy Ltd. Unit-IV |
|---|---|
| Status | Environmental approval granted |
| Status since | 1 Aug 2024 |
| Application filed | 3 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Trualt Bioenergy Limited |
| Land area | 28.3 acres (11.5 ha) |
| Project cost | ₹650 crore |
| Village / locality | Jalageri |
| Taluk / tehsil | Badami |
| District | Bagalkote |
| State | Karnataka |
| Location from | Site area on record |
| Our reference | WID-KA-02755 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 16 Sept 2025 | Returned to applicant | 28.3 acres | ₹650 crore |
| New project filed 3 Apr 2024 (this page) | Environmental approval granted | 28.3 acres | ₹650 crore |
| Early planning filed 28 Jul 2023 | Cleared for impact study | 28.3 acres | ₹650 crore |
In context
61 applications in Bagalkote since January 2022 are in the same category (Industry): 39 approved, 11 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 28.3 acres, this one is smaller than 80% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jalageri, Badami, Bagalkote, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane… — returned to applicant, 0 m away
- Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane… — cleared for impact study, 0 m away
- Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane… — withdrawn, 0 m away
- Expansion of Sugar Mill from 3500 TCD to 10000 TCD, Co-Generation Power Plant… — lapsed, 150 m away
- 60 KLPD Molasses based distillery & 18 MW Co-generation power plant by M/s.… — cleared for impact study, 200 m away
- 60 KLPD Molasses based distillery & 18 MW Co-generation power plant by M/s.… — lapsed, 200 m away
- Expansion of Sugar Mill (3500 TCD to 15000 TCD), Co-generation Power Plant (15… — lapsed, 250 m away
- Expansion of Sugar Mill (3500 TCD to 15000 TCD), Co-generation Power Plant (15… — cleared for impact study, 250 m away
More from Trualt Bioenergy Limited in Bagalkote
- Expansion of 200 KLPD ENA/RS/Ethanol with cane syrup/molasses based to 700… — cleared for impact study
- Expansion of Distillery from 120 KLPD to 700 KLPD for manufacturing of RS/… — returned to applicant
- Manufacturing of RS/ ENA/ Industrial Alcohol / Sustainable Aviation Fuel (SAF)… — cleared for impact study
- Use of Additional Feedstock – Grain in Addition to the Existing Feedstocks… — lapsed
- Expansion of Distillery for Ethanol Production Under Ebp Program From 700 Kld… — environmental approval granted
- Transfer of Distillery Section in the Environment Clearance Granted for the… — lapsed
All 10 Trualt Bioenergy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.