All projects, newest first
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Derenga & Khajuria Sand Quarries Cluster Over an Area of 30.0 Acres Or 12.14 Hectares Deranga, Kaniha | Mining | 30 acres | Lapsed | 29 Jun 2024 |
| New Proposal for Amendment EC of Ghodamara Ghat Sand Quarry, Kaintragarh over an area of… Barapal, Athmallik | Mining | 12 acres | Environmental approval granted | 25 Jun 2024 |
| Expansion of Existing 1200MW by adding 3rd and 4th Unit of 660 MW ULTRA SUPERCRITICAL… Deranga, Kaniha | Power | 1,350.1 acres | Lapsed | 20 Jun 2024 |
| Expansion of 5.6 Mtpa Steel Plant Through Change in Product Mix by Establishing 2.6 Mtpa… Ganthigaria, Banarpal | Industry | 29.7 acres | Environmental approval granted | 19 Jun 2024 |
| Expansion of Aluminium Smelter Plant production capacity from 4.6 LTPA to 9.57 LTPA at… Gopinathapur, Nalco | Industry | 1,186.9 acres | Cleared for impact study | 4 Jun 2024 |
| Haturipal Brahmani Sand Quarry over an area of 11.80 Acre or 4.77 Ha Haturipal, Talcher Sadar | Mining | 11.8 acres | Environmental approval granted | 16 May 2024 |
| 200 Beded Multi speciality Hospital at: Kangula, Tahasil- Anugul, Dist: Anugul, Odisha… Kangula, Banarpal | Buildings & townships | 4 acres | Lapsed | 14 May 2024 |
| Modification of Ec on the Basis of Replenishment Study Report of Kampasala Sand Quarry… Kampasala, Chhendipada | Mining | 7.4 acres | Not approved | 6 May 2024 |
| Environmental Clearance for Production of country Liquor from the manufacturing unit of… Purunakot, Purunakot | Industry | 0.4 acres | Environmental approval granted | 21 Apr 2024 |
| Environmental Clearance for Production of country Liquor from the manufacturing unit of… Natara, Anugul | Industry | 0.2 acres | Environmental approval granted | 5 Apr 2024 |
| Environmental Clearance for Production of country Liquor from the manufacturing unit of… Nuata, Banarpal | Industry | 0.7 acres | Environmental approval granted | 4 Apr 2024 |
| Laying of Optical Fibre Cable(OFC) under 4G Saturation project of USOF, Govt. of India. Karadaberenijungle, Purunakot | Telecom | ₹1.1 crore | More information requested | 25 Mar 2024 |
| Laying of Optical Fibre Cable(OFC) under 4G Saturation project of USOF, Govt. of India. Pampasar, Purunakot | Telecom | 2.6 acres | More information requested | 25 Mar 2024 |
| Improvement of Road and CD works of Pitabahal Chhak to Bipradihi via Taranda under PMGSY… Forest, Thakurgarh | Roads & highways | 2.4 acres | More information requested | 12 Mar 2024 |
| Diversion of 13.0 Ha Forest Land Out of Total 312.697 Ha of Utkal D & E Combined Forest, Jarapada | Mining | 32.1 acres | Forest land use approved | 18 Feb 2024 |
| Re-Diversion of 299.697 Ha Forest Land Out of Total 312.697 Ha of Utkal D & E Combined. Raijharan, Industrial | Mining | 2,004.8 acres | Forest land use approved | 18 Feb 2024 |
| 2 x 525 MW Coal Based Thermal Power Plant Balichandrapur, Industrial | Power | 988.4 acres | Environmental approval granted | 28 Jan 2024 |
| Application for Amendment of Ec for Mining of Sand From Nizagarhzami Sand Quarry Over an… Nijigadjami, Colliery | Mining | 24.9 acres | Not approved | 27 Jan 2024 |
| Expansion of Bharatpur Ocp of Existing Capacity 20 Mtpa With Additional Lease Area From… Chintamanipur, Colliery | Mining | 3,847.3 acres | Lapsed | 20 Jan 2024 |
| Proposed Common Biomedical Waste Treatment Facility (CBWTF)At: Khata No:552/149, Plot… Seepur, Samal Barrage | Waste management | 10.6 acres | Cleared for impact study | 9 Jan 2024 |
| District Survey Report (DSR) of Angul District for Sand, Stone, Morrum, Laterite… Aanda, Khamar | Mining | Lapsed | 29 Dec 2023 | |
| Sirigida Sand Quarry Present in River Brahamani Over an Area of 18.00 Acres (7.28 Ha.) Sirigida, Talcher Sadar | Mining | 18 acres | Environmental approval granted | 28 Dec 2023 |
| Bajrakote Send Quarry over an area of 11.83 acres or 4.79 hectares bearing Khata no:… Bajrakote, Rengali Damsite | Mining | 11.8 acres | Environmental approval granted | 14 Dec 2023 |
| Proposed Intake Water Pipeline Corridor for Ttps Expansion Project(2 X 660MW) by NTPC Belapada, Talcher Sadar | Pipelines | 4,953.3 acres | Forest land use approved | 12 Dec 2023 |
| Bhubaneswari Opencast Expansion Project Arakhapal, Talcher Sadar | Mining | 1,627.7 acres | Cleared for impact study | 4 Dec 2023 |
| Amendment in Ec W.R.T. Amalgamation of Environmental Clearance of Utkal D and Utkal E… Kosala, Chhendipada | Mining | 2,131.4 acres | Returned to applicant | 29 Nov 2023 |
| Naini Coal Mine Thalipasi, Chhendipada | Mining | 2,255.6 acres | Environmental approval granted | 23 Nov 2023 |
| Change in Land Use Pattern of 6.682 Hect. of Forest Land Diverted for Laying of Railway… Sanakerjang Jungle, Industrial | Railways & metro | 130.2 acres | Lapsed | 23 Nov 2023 |
| Hidsing Irrigation Project Karatpata, Bantala | Water & irrigation | 8,794.9 acres | Under wildlife review | 10 Nov 2023 |
| Diversion of combined Utkal- D & Utkal- E Coal Mines by M/s NALCO. Kundajharijungle, Industrial | Mining | 2,036.9 acres | Lapsed | 30 Oct 2023 |
| Subhadra Open Cast Project Forest, Jarapada | Mining | 2,747.4 acres | Environmental approval granted | 12 Oct 2023 |
| Jagannath OCP Expansion Nakhetrapur, Colliery | Mining | 1,429.3 acres | Lapsed | 30 Sept 2023 |
| Baitarni West Opencast Coal Mine with production capacity of 15 MTPA in an area of 1196 ha Forest, Chhendipada | Mining | 2,955.4 acres | Cleared for impact study | 23 Sept 2023 |
| Greenfield Project of 250 KL/Day Grain Based Ethanol Plant by M/s Asva Distillers LLP Ghodagadi, Kiakata | Industry | 30 acres | Environmental approval granted | 29 Aug 2023 |
| Safety Zone of Utkal B1 Coal Mine Kaunsidhipa, Industrial | Mining | 102.2 acres | Lapsed | 28 Aug 2023 |
| Tainsar Sand Quarry over an area of 48.42 acres or 19.595 Ha bearing khata No. 72, Plot… Taensar, Athmallik | Mining | 48.4 acres | Environmental approval granted | 21 Jul 2023 |
| Hidising Irrigation Project Kararasinga, Purunakot | Water & irrigation | 6.4 acres | More information requested | 9 Jun 2023 |
| Change in Land Use Pattern of 6.682 Hect. of Forest Land Diverted for Laying of Railway… Raijharan, Industrial | Railways & metro | 130.2 acres | Lapsed | 24 May 2023 |
| 2 x 525 MW Coal Based Thermal Power Plant Balichandrapur, Industrial | Power | 988.4 acres | Cleared for impact study | 13 Apr 2023 |
| Approach Road for Utkal D&E Forest, Jarapada | Roads & highways | 0.9 acres | Forest land use approved | 20 Mar 2023 |
| Takua Sand Quarry over 8.30 ha onTikira River Takua, Kaniha | Mining | 20.5 acres | Cleared for impact study | 11 Feb 2023 |
| Prospecting of Alaknanda Coal Mine of M/S Rungta Sons PVT LTD Baraberana, Chhendipada | Mining | 2,756.4 acres | Forest land use approved | 7 Feb 2023 |
| Bhubaneswari Opencast Expansion Project Ambamunda, Talcher Sadar | Mining | 1,947 acres | Environmental approval granted | 29 Jan 2023 |
| Radhikapur (West) Coal Mine Block (Opencast cum Underground)(ML Area: 1048 Ha) with… Balipata, Chhendipada | Mining | 2,589.7 acres | Environmental approval granted | 30 Nov 2022 |
| Environmental Clearance for production of 9000 Cum/annum of River Sand over Hathuripal… Haturipal, Talcher Sadar | Mining | 26.5 acres | Environmental approval granted | 21 Nov 2022 |
| Expansion of Pellet Plant from 5.0 MTPA to 26.0 MTPA and Hot Rolling mill from 3.1 MTPA… Sanakerajang, Industrial | Industry | 3,609 acres | Environmental approval granted | 15 Nov 2022 |
| Diversion of 2.1 Ha of Forest Land for Construction of Pmgsy Road From Pitabahal Chhak… Kenchuanali, Thakurgarh | Roads & highways | 5.2 acres | Lapsed | 14 Oct 2022 |